Construction

Construction updates

Stay Informed

 

Destination Brisbane Consortium is the project developer responsible for the design, approval and construction of Queen’s Wharf Brisbane.

Queen’s Wharf Brisbane is the largest construction project in Queensland and at its peak will employ nearly 2,000 people.

The consortium has chosen to break the construction down into multiple contractors for different work packages. These include:

  • Demolition (completed December 2017)
  • Excavation (completed July 2019)
  • Mangrove Walk, Bicentennial Bikeway and Waterline Park (completed September 2019)
  • The Landing structural works (completed September 2020)
  • Neville Bonner Bridge (started March 2020)
  • Shell and core construction of Integrated Resort Development (started July 2019)
  • Internal fit-out of Integrated Resort Development (started July 2021)
  • Public realm including Bicentennial Bikeway upgrade, architecturally designed parks, Velo Café and amenity block (started March 2021)
  • Heritage base works including structural support work (started August 2021)

Destination Brisbane currently has two contractors engaged – Multiplex and Fitzgerald.

Multiplex is responsible for the main integrated resort development and public realm works along the Bicentennial Bikeway and Queens Wharf Rd and Fitzgerald is responsible for the Neville Bonner Bridge construction.

QWB Map

Standard construction hours are from 6.30am to 6.30pm Monday to Saturday. Currently, Multiplex is approved to undertake night works (excluding Friday and Saturday nights) and outside these hours construction notices are issued and uploaded to the website under construction.

To stay informed about the project and construction activities please subscribe to our monthly e-newsletter or sign-up for construction updates by following the stay informed tab at the top of this page.

Destination Brisbane Consortium is excited to be building this transformational city changing project for Brisbane and we thank the community for their patience while this work is undertaken.

For general enquiries please contact the Consortium direct on 1800 104 535 or email qwbenquiries@destinationbrisbane.com.au.

Slide through to see Queen’s Wharf Brisbane evolve

Construction Updates

  1. Completed

    Update: Night works on Margaret Street: In-bound traffic take Elizabeth Street or Turbot Street off-ramps from the Riverside Expressway

    Revised dates: From Sunday 22 August 2021, nights work and temporary traffic detours will be required to upgrade stormwater connections on Margaret Street.   When: Night works are scheduled five nights per week – Sunday to Thursday between 8pm and 5am. This is the first stage of stormwater connection works that will continue for approximately […]
  2. Completed

    Night works on George Street to upgrade watermain connection

    George Street, between Charlotte and Margaret Streets will be closed to traffic in one or both directions, at night, for five weeks starting Thursday 12 August 2021. When: Night works are scheduled from Sunday to Thursday between 8pm and 5am over five weeks (excluding Friday and Saturday nights). The night works are necessary to minimise […]
  3. Completed

    Temporary lane closure for material load-out on George Street

    From 2 August 2021 for four weeks, works will be required for removal of non-heritage material from the Printery Building. A temporary loading bay will be established on George Street for material load-out. When: From Monday 2 August 2021 until late August, works will be required between 6.30am and 4pm Monday to Friday (pending weather […]
  4. Completed

    Temporary detour at South Bank while overhead works restrict access to Clem Jones Promenade

    On Wednesday 28 and Thursday 29 July 2021 precast concrete will be installed on the Neville Bonner Bridge deck that spans the Clem Jones Promenade. When: On Wednesday 28 July and Thursday 29 July between 9:30am and 3:30pm, bridge contractor Fitzgerald Constructions will require a temporary closure of the Clem Jones Promenade to install the […]
  5. Completed

    Night works for material load-out on George Street

    From 19 July 2021 for four weeks, night works will be required for removal of non-heritage material from the Printery Building. Each night, a temporary loading bay will be established on George Street for material load-out. When: From Monday 19 July 2021 until late August, works will be required at night between 8pm and 6am […]
  6. Completed

    Future public realm requires vegetation removal along the Bicentennial Bikeway and in Miller Park

    In three work stages starting 6 July 2021 vegetation, including many invasive species, will be removed from areas adjacent to the Bicentennial Bikeway and in Miller Park. When: From 6 July until late – September 2021 vegetation removal will occur periodically as Multiplex progresses into new riverside public realm work areas. Much of the vegetation […]
  7. Completed

    Stephens Lane to close to pedestrian and vehicular access

    From 21 June 2021 Stephens Lane will be closed for vehicle and pedestrian access. It will reopen as a walkway in late-2022 with the integrated resort development. When: From Monday 21 June 2021 until late-2022 Stephens Lane will be closed to vehicle and pedestrian access, becoming a construction zone for heritage building works and resurfacing. […]
  8. Completed

    Temporary gantry to be installed on Bicentennial Bikeway near The Landing area

    A temporary gantry to be installed as a safety measure for when the bridge deck section is lifted in over the Riverside Expressway. When: Night works: The gantry will be installed between 7:00pm Tuesday 15 June 2021 and 4:30am Wednesday 16 June 2021. The gantry will remain in position until its dismantling operations planned to […]
  9. Completed

    Riverside Expressway temporarily closed for major bridge deck lift

    A significant section of the Neville Bonner Bridge will be lifted into position above the expressway requiring a weekend closure for traffic in both directions When: From 10pm Friday 18 June until 5am Monday 21 June 2021. Where and why: The Riverside Expressway will be closed to traffic in both directions between Elizabeth St and […]
  10. Completed

    Temporary closure to Clem Jones Promenade, South Bank, first bridge module lifted into position

    On Tuesday 15 June 2021 the first section of bridge will be installed from the South Bank abutment to a temporary support structure in the Brisbane River When: Between 9:30am and 2:00pm on Tuesday 15 June 2021, bridge contractor Fitzgerald will install the first deck module over the Clem Jones Promenade at South Bank. Where: […]